  • Movable Iron PIT
  • Sludge Box
Movable Iron PIT
MovableIron- PIT
Reduction of expense according to mobility /The tire washing system site is easy to install and thus reduces production costs
Sludge Box
Sludge Box

PIT 3D Drawing

* This basic drawing is for right-moving direction. (For left-moving direction, please contact us.)

Foundation construction progress

* This basic drawing is for right-moving direction. (For left-moving direction, please contact us.)
* Tail plate is optional.
  1. 01
    Selection of the tire washing system location
  2. 02
    Excavation commencement
  3. 03
    Excavation completion
  4. 04
    Rubble sorting
  5. 05
    Vinyl packaging and concrete leveling
  6. 06
    Distribution of foundation reinforcement
  7. 07
    Completion of floor concrete placing (5,200x7200xT:200)
  8. 08
    Installation of tire washing systems
  9. 09
    Installation of tire washing systems
  10. 10
    Refilling
  11. 11
    Backfilling and compacting work on entry and exit
  12. 12
    Reinforcement work on entry and exit (Specification: Iron D13@200)
  13. 13
    Concrete pouring on entry and exit
  14. 14
    Complete basic construction